I took the day off from work today to meet the site supervisor so that I could take a look around at the progress. It looks like our early November move in date is now officially looking more like a late November move in date. It's very unlikely we'll be in on time. A little disapointing on a 34 week build, but I guess a week or 2 isn't too bad. The tilers were in again today, finishing off the ensuite. The kitchen looks good, but the breakfast bar is the wrong type and will have to be pulled back out and swapped over. The first layer of paint is on. All conrnices are done. The bathroom cabinets are all in. It's really starting to look like a house.